Expanding finance-based scheduling to devise overall-optimized project schedules

  • Ashraf M. Elazouni*
  • , Fikry G. Metwally
  • *Corresponding author for this work

Research output: Contribution to journalArticlepeer-review

51 Scopus citations

Abstract

Construction contractors often finance projects using bank credit lines that allow contractors to withdraw money up to certain credit limits. Finance-based scheduling provides schedules that ensure that the contractor's indebtedness at any time during the construction stage does not exceed the credit limit. Generally, constricted credit limits tend to yield prolonged schedules. Provided that credit limits can be adequately relaxed, compressed schedules of compressed-duration activities can be attained. Devising a compressed schedule calls for the incorporation of time-cost trade-off (TCT) analysis to strike a balance between the decreased overhead costs and the increased direct costs of the activities. Since employing TCT analysis usually causes great fluctuations in the daily resource requirements by mixing compressed-duration activities of high resource demand with others of low resource demand, therefore, the need for resource management techniques becomes inevitable to ensure efficient utilization of resources. This note used genetic algorithms to expand finance-based scheduling to devise schedules for relaxed credit limits. A prototype system was developed and coded using VISUAL BASIC, then demonstrated using a five-activity example project. The prototype was validated by comparing the results with those obtained by using the integer programming. Expanding finance-based scheduling to handle the whole spectrum of credit limits helps devise overall-optimized schedules that consider cash, time, cost, and resources.

Original languageEnglish
Pages (from-to)86-90
Number of pages5
JournalJournal of Construction Engineering and Management
Volume133
Issue number1
DOIs
StatePublished - 2007

Keywords

  • Algorithms
  • Construction management
  • Contractors
  • Financial management
  • Optimization
  • Scheduling

ASJC Scopus subject areas

  • Civil and Structural Engineering
  • Building and Construction
  • Industrial relations
  • Strategy and Management

Fingerprint

Dive into the research topics of 'Expanding finance-based scheduling to devise overall-optimized project schedules'. Together they form a unique fingerprint.

Cite this