Devising extended-duration schedules of enhanced resource leveling

  • Mohammed Abdul Rahman
  • , Ashraf Elazouni*
  • *Corresponding author for this work

Research output: Contribution to journalArticlepeer-review

3 Scopus citations

Abstract

The use of resource management techniques is crucial to resolve conflicts and achieve the efficient utilization of resources. Particularly, resource-leveling techniques schedule activities in unconstrained-resource conditions to minimize fluctuations in resource profiles. According to the literature, resource leveling has typically been performed by considering that the original project duration remains fixed. Virtually, some extension in the project duration might be acceptable should a considerable enhancement in resource leveling be achieved. This paper enhances resource leveling through devising schedules of extended duration that exhibit resource profiles of lower fluctuation. Critical path method (CPM) networks of extended total floats are utilized to provide expanded yet definite spaces to search for schedules of lower resource fluctuation. The modified CPM networks accommodate for employing optimization models and searching optimal or near-optimal solutions. For demonstration, a genetic algorithm model was formulated to solve two case-study networks of 30 and 120 activities. The results indicate that schedules of lower fluctuation in resource profiles were obtained beyond the original networks’ duration.

Original languageEnglish
Pages (from-to)552-562
Number of pages11
JournalCanadian journal of civil engineering
Volume42
Issue number8
DOIs
StatePublished - 1 Jun 2015

Bibliographical note

Publisher Copyright:
© Published by NRC Research Press.

Keywords

  • Genetic algorithm
  • Optimization
  • Resource leveling
  • Scheduling

ASJC Scopus subject areas

  • Civil and Structural Engineering
  • General Environmental Science

Fingerprint

Dive into the research topics of 'Devising extended-duration schedules of enhanced resource leveling'. Together they form a unique fingerprint.

Cite this